Request for Qualifications: WTP and WWTP Standby Generators Engineering

Statements of Qualifications are due Monday, December 7, 2026, at 2:00 p.m. Eastern Time, by email.

The Town of Stuart, Virginia, requests Statements of Qualifications from qualified professional engineering firms to design permanent standby generators and automatic transfer switches at the Town’s water treatment plant and wastewater treatment plant and a portable generator, transfer switch, and generator connection for the raw water intake pump station, and to provide bidding and construction phase services, including resident project representation. The work is funded by a U.S. Department of Agriculture, Rural Development grant (Assistance Listing 10.760) and Town funds and will be procured through qualifications-based selection consistent with the Brooks Act (40 U.S.C. 1101 to 1104) and 2 CFR 200.320(b)(2)(iv). Price is not a selection factor.

Request for Qualifications, issued November 5, 2026 (PDF, 29 pages)

Key Dates

  • RFQ issued: Thursday, November 5, 2026
  • Written questions due: Monday, November 23, 2026, 5:00 p.m. Eastern Time, by email to the Owner’s Representative
  • Statements of Qualifications due: Monday, December 7, 2026, 2:00 p.m. Eastern Time. Late submittals will not be considered.

How to Submit

Submit one electronic copy of the Statement of Qualifications as a single searchable PDF file no larger than 25 MB, by email to bryce.simmons@stuartva.org, with the subject line “SOQ: Stuart WTP and WWTP Generators Engineering.” The Town will confirm receipt by reply email. Submitters are responsible for timely delivery, and the time of receipt shown in the Town’s email system governs. Paper, mailed, and hand-delivered submittals will not be accepted. A firm responding to both of the Town’s November 5, 2026 engineering solicitations must submit a separate SOQ for each.

Information Available to Submitters

As described in Paragraph 2.03 of the RFQ:

Items 3 and 4, record drawings of the electrical service and distribution at each site and electric utility service information with twelve months of billing demand data, will be issued by Addendum No. 1, which the Town expects to issue by November 13, 2026.

Questions and Addenda

Submit questions in writing by email to the Owner’s Representative by the deadline above. Answers will be issued by addendum. Firms must provide a contact email address to the Owner’s Representative to receive addenda.

Addenda will be posted on this page as they are issued. No addenda have been issued as of November 5, 2026.

Related Solicitation

The Town is also requesting qualifications, with the same submittal deadline, for evaluation and design of flow equalization and septage receiving and an inflow and infiltration study at its wastewater treatment plant, funded by a U.S. Environmental Protection Agency Community Grant. A firm may submit for both; each is evaluated separately. See the WWTP equalization RFQ.

Small businesses, minority-owned businesses, women-owned businesses, and veteran-owned businesses are encouraged to submit as prime firms or as subconsultants. A firm that subcontracts any part of the services must take the steps 2 CFR 200.321 requires for its subcontracts.

Owner’s Representative

Bryce M. Simmons, PE, Town Manager
Town of Stuart, 100 Patrick Avenue, PO Box 422, Stuart, VA 24171
bryce.simmons@stuartva.org | 276.694.3811

The Town of Stuart does not discriminate on the basis of race, color, national origin, sex, age, or disability in its programs and activities. This institution is an equal opportunity provider and employer.

Date of Notice: November 5, 2026